PNC Infratech (PNCL) delivered weak 2QFY17 APAT (~34.5% below estimates), on account of delay in NHAI awarding compensation to land owners as per new land bill. This impacted execution on Rs 30bn worth projects (~55% order backlog). PNCL expects the issue to be sorted out by 4QFY17E with all the projects moving into execution.