Order inflows impacted by delays in project finalisation During Q3FY20, order inflow came in at | 5950 crore, down 22.7% YoY, (| 3240 crore from power segment, | 2230 crore from industrial segment, | 480 crore from exports segment) while 9MFY20 inflows stands at | 17000 crore. Bhel's order backlog as on Q3FY20 was at | 107654 crore, of which executable order book is ~ | 87495 crore. Bhel is favourably placed in orders worth ~| 13000 crore (Talcher plant- | 6300 crore, FGD- | 4200 crore, industry segment- | 900 crore). However, few projects in power sector...