Q4FY19 revenue grew by 42% YoY to Rs1,076cr led by strong execution of big ticket order book. While FY19 revenue growth remain strong at 67% YoY to Rs3,097cr. The strong execution is likely to continue as PNC has already received appointed date for six HAM projects while Challakare to Hariyur project appointed date is awaited. The unexecuted potion of the HAM projects constitute 48% of the total order book. Total equity requirement for all HAM projects is Rs832cr of which PNC has already infused Rs232cr and balance will invest over the next two to three years. Additionally, Nagpur Mumbai...