The present manufacturing facilities have been operating at ~95% utilisation level. Hence, the company is coming up with incremental capex of 52,000 MTPA Ambernath (32,000 MTPA), Patalganga (10,000 MTPA) and another 10,000 MTPA capacity in JV with German partner Adcotec, of which Ambernath facility will get commissioned by the end of this month (June 2019), while the same at Patalganga is expected to get commissioned by FY21. Capex has been earmarked to the tune of | 150-160 crore for Ambernath and | 65 crore for Patalganga. The Ambernath facility will have...