In continuation to our earlier letters dated 23.10.2023, 22.05.2024 and 13.11.2024 and in compliance to Regulation 30 of SEBI (LODR), it is to inform that trial run of Unit#2 (200 MW) of Parbati-II HE Project (4x200 MW), Himachal Pradesh has been successfully completed on 24.03.2025. The trial run of balance 3 units of Parbati-II HE Project is expected to be completed by 31.03.2025.