INR12.4b) on the back of resumed income recognition for its Subansiri project (since 1QFY20). Construction on NHPCs Lower Subansiri (2,000MW) project has restarted from Oct19. NHPC expects the project to be completed by 2QFY24. Company expects the project to be commissioned in FY22 (unchanged). Capex run- rate, on the other hand, is expected to increase as the company is investing/ exploring new projects. in prior quarter numbers Management has noted that work on Subansiri project has resumed and the project is expected to be completed by 2QFY24. The tender for Power house is yet to be awarded and company is in the process The project requires a tunnel of 31km, of this, 2.5km is yet to be completed and NHPC expects the project to be commissioned in FY22. Company expects the project to be completed in 5 years time.